Weekly Construction Activity Update                        

Planned activities are as follows for the week of 11/8/2010:

Infrastructure:

This multi-faceted project will upgrade the old, unreliable infrastructure system and get the campus ready for future growth.

Central Plant:  Contractors continue the process of commissioning the hot and cold water systems.

Central Plant Chiller Room

Central Plant Heating Equipment

Parking Lot A7:

Please be advised that beginning Tuesday, October 19th, the parking lot just West of Malibu Hall will be closed for renovation.  As a reminder, overflow parking for staff and faculty can be found just West of Chaparral Hall.

Ironwood Hall Paving:

The Ironwood Hall, Central Plant, Maintenance Stores, Substation, and Cogen Plant areas will receive new asphalt.  Operations will include grading and installing new asphalt behind Ironwood Hall.  The Cogen Plant road and the Corporation Yard's existing paving will be pulverized and recycled prior to re-paving, to help preserve our resources.

Initial grading started Monday, November 1st, 2010.  The finish grading for the re-paving continues and the asphalt paving operation is scheduled for Monday, 11-8-2010.  Please expect increased truck traffic and noise from trucks during the paving operation.

North Hall:

This project included the demolition of portions of the existing structure, interior demolition and renovation of the remaining building, and new construction centered at the south end of the North Quad.  It will include one 120-seat lecture hall, seven lecture classrooms (totaling 315 stations), three computer labs, lecture/lab support spaces, faculty offices, administrative offices and ancillary support spaces.

Demolition of interior walls and existing window openings continues.  Excavation for the new three stop building has begun.  Click here for a revised pedestrian path of travel map to Nursing Simulation Lab.

Artist Rendering of North Hall

Entrance Road:

This project includes the construction of a new 4 lane lighted Entrance Road crossing a 153 acre site from Lewis Road to the central campus.

Bids were received on 9/9/2010 and Notice to Proceed is expected to be issued in early October.  For a short animation clip of the proposed road click here: CI Entrance Road Video

Renovation and Repair Updates for the week of 10/18/2010

Campus Storm Drain Outfall Repair:

The storm drain outfall area has become overgrown and filled with debris, this repair will clear all shrubs and debris from the area, expose the outfall pipe and create a new rock outfall protection apron that will help out storm water flow without issue.

The area is now being cleared of vegetation and overgrowth; crews will expose the storm drain pipe this week and start reworking the outfall drainage area.

 

Bell Tower Restroom Repairs:

Bell Tower men's restroom 1421 and women's restroom 1425 are currently closed for repairs.  Alternate restrooms are available in the area and directional signage has been placed to identify the route to them.  OPC crews and contractors will be working on the repairs on and off hours and hope to have the restrooms reopened by 10/15/2010.

New Drywall, tile and paint has been installed on the plumbing walls and the plumbing fixtures have been replaced.  These restrooms repairs are now complete and open for use.

Bell Tower Restroom Repair 

Santa Cruz Repairs F Building:

Water damage to exterior of F building has occurred and areas of the stucco will need to be removed down to the sheathing and replaced with new.  Crews are to begin the repairs on 9/20/10 and will work to be complete by 10/22/2010.

New sheathing, moisture protection and stucco has been installed and the color applied -  this project is now complete.http://collage.csuci.edu/servlet/frame_contribution_edit.jsp?assetid=67028&aType=OPC_PG

Santa Cruz Stucco Repairs

Napa Hall Exterior Paint:

Napa hall has just been renovated inside, the building exterior (East, South and West sides) will be refreshed with exterior paint, trimming some existing trees around the building and debris removal from the tile roof facing North Quad.

The building has been primed and finish coated and the windows have been painted.  Final touch ups will occur this week.

Napa Hall Paint

Archive Courtyard at Broome Library:

The Archive Courtyard at the Broome Library has received new hardscape and landscape, OPC crews will now paint the exterior walls and replace some doors that are in disrepair.

The pressure washing is complete, patchwork, prime and paint operations will continue and the doors will be replaced once received.

Archive Courtyard

Student Union Crawl Space Access and Lighting Upgrade:

The original wing of the Student Union Building has only one access point into the crawl space which makes it a Permit Required Confined Space, Operations crews will be installing additional access points and installing lighting under the building for crews that need to work on the utilities.

The access doors are being fabricated and will be installed soon, the lighting phase of the project has begun and new fixtures and maintenance outlets are being installed.

Student Union Crawl Space Lighting

As always, we appreciate your patience and support. 